4th
December 2011
The overhaul
of the replacement ‘B’ end engine progresses well.So far the engine block has been cleaned internally and externally and externally repainted and
partially rebuilt in the groups workshop before being moved to the D&EG workshop at Williton
to use the turnover stand they have there.
The engine stand was also derusted, cleaned and
repainted and transported with the short engine and the rebuild is continuing rapidly.
All the associated engine pipework, engine room doors and flooring have been cleaned and
repainted as required in the workshop.
The failed engine has been removed from the loco and stripping is almost complete.
Meanwhile the engine room has been thoroughly cleaned to a very high standard and only
some of the pipework will need repainting.
Two frost damaged air pipes have been removed to the workshop and repaired and repainted
and refitted to the loco and a new water pump seal has been made.
The replacement bogie has been completely stripped at Washwood Heath and the frame cleaned
and tested for fatigue cracks and those found have been repaired.
The wheelsets have successfully passed their ultrasonic test.
All the bogie brake cylinders have been stripped down, cleaned, overhauled, rebuilt and
externally repainted in the workshop.
New brake hanger bushes have been manufactured and the brake gear overhauled, rebuilt and
repainted also in the workshop.
22nd November 2011
Below are
pictures from recent work done by DTG Working Party covering up D1015 for Winter Hibernation at Tyseley!.
Below All photos from Paul Winter
.